La Lupa

Project of TeraWulf

Kind
datacenter
Location
Lake Mariner, New York
County
Niagara
State/region
NY
Country
US
Status
announced

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today60 MW IT load2026-04-15Core42 data center lease
Contracted a customer is on the hook60 MW IT load2026-09-01La Lupa - Core42 Data Center Lease - 60 MW
Under construction--
Permitted--
Interconnect approved utility has agreed to deliver--
Interconnect requested in a queue, nothing approved--
Announced a press-release figure75.2 MW2026-09-01La Lupa project data centre capacity

Who has claimed this site

Capacity commitments in the order they were announced. A commitment that ended shows why.

2026-02-26
Core42 - tenant · 60 MW · 10-year term source

Claims about this project

2026-02-26 - stated
2026-02-26 - stated
2026-04-13 - stated
2026-04-14 - stated
2026-04-15 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - delayed
La Lupa data center additional capacity online 50.0 MW. Promised by 2025-12-31.