CB-2 delivery Q4 2025

Company: TeraWulf - Project: La Lupa

This claim was marked delayed on October 13, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2025-08-14
Promised by
2025-12-31
Current status
delayed

What the later record shows

The date slipped

In November 2025 an additional 50 MW for Core42 was still pending. By December 31, 2025 only 18 critical IT MW was energized, and the remaining leases were expected to commence in 2026, so CB-2 missed Q4 2025.

“TeraWulf remains on track to deliver an additional 50 MW of HPC leasing capacity under its datacenter lease agreements with Core42 Holding US LLC”
2025-11-09 · TeraWulf 10-Q filed 2025-11-10 View cached copy (2026-08-31)Live source ↗
“Certain of the Core42 HPC Leases commenced in 2025 and the remainder of the HPC Leases are expected to commence in 2026.”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked October 13, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

CB-2 (Core42 capacity at Lake Mariner) is on track for delivery in Q4 2025.

Source (primary)

Q2 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-13)Live source ↗

Quote: “CB-2 on track for Q4 delivery”

How we checked this

Checked on October 15, 2026. The cited source supports every part of this claim.

The update lists CB-2 under delivering Core42 capacity at Lake Mariner and states it is on track for Q4 delivery.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_513c80c486e62e4bdb70115ded3782f5/terawulf/db/2396/23302/pdf/WULF_Q2_2025_Investor_Update_%28Aug_2025%29vF.pdf) in full (17,599 characters, retrieved October 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Q2 Earnings Update Presentation

Quote: “CB-2 on track for Q4 delivery”

View cached copy (2026-10-13)Live source ↗

delays TeraWulf 10-Q filed 2025-11-10

Quote: “TeraWulf remains on track to deliver an additional 50 MW of HPC leasing capacity under its datacenter lease agreements with Core42 Holding US LLC”

View cached copy (2026-08-31)Live source ↗

delays View 10-K PDF

Quote: “Certain of the Core42 HPC Leases commenced in 2025 and the remainder of the HPC Leases are expected to commence in 2026.”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

October 13, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 13, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.