CB-2 data centre operations start

Company: TeraWulf - Project: La Lupa

This claim was marked delayed on October 9, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2025-10-14
Promised by
2025-11-30
Current status
delayed

What the later record shows

The date slipped · new target December 31, 2025

In November 2025 the CB-2 50 MW was restated as delivering around year-end rather than in November. Only 18 critical IT MW was energized at 2025-12-31, and the company later cited timing impacts from tenant fit-out enhancements.

“La Lupa 22.5 of capacity online and another 50 MW delivering around year-end subject to tenant fit-out requests”
2025-11-10 · Investor Presentation View cached copy (2026-10-06)Live source ↗Archive.org ↗
“Certain building milestones were sequenced accordingly, and associated timing impacts have been incorporated into the Company’s financial plan.”
2026-02-25 · terawulf 8-K exhibit (a_wulfearningsrelease2026-.htm) View cached copy (2026-09-13)Live source ↗
“As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity and remains on track to deliver additional contracted capacity”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

CB-2 data centre at Lake Mariner (Project La Lupa) is expected to commence operations in November 2025.

Source (primary)

TeraWulf Sustainable Finance Framework Second Party Opinion 2025 (IR page (investors.terawulf.com), ir_release)
View cached copy (2026-10-06)Live source ↗Archive.org ↗

Quote: “while CB-2 is expected to commence operations in November 2025”

How we checked this

Checked on October 14, 2026. The cited source supports every part of this claim.

The document lists CB-2 as part of Project La Lupa at Lake Mariner. It says CB-2 was expected to start operations in November 2025.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2476/23465/pdf/TeraWulf_Sustainable_Finance_Framework_Second_Party_Opinion_2025.pdf) in full (29,307 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf Sustainable Finance Framework Second Party Opinion 2025

Quote: “while CB-2 is expected to commence operations in November 2025”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

delays View 10-K PDF

Quote: “As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity and remains on track to deliver additional contracted capacity”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

delays terawulf 8-K exhibit (a_wulfearningsrelease2026-.htm)

Quote: “Certain building milestones were sequenced accordingly, and associated timing impacts have been incorporated into the Company’s financial plan.”

View cached copy (2026-09-13)Live source ↗

delays Investor Presentation

Quote: “La Lupa 22.5 of capacity online and another 50 MW delivering around year-end subject to tenant fit-out requests”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms TeraWulf Sustainable Finance Framework Second Party Opinion 2025

Quote: “while CB-2 is expected to commence operations in November 2025”

View cached copy (2026-10-13)Live source ↗Archive.org ↗

Record of changes

October 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 7, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-10-06 was the source's retrieval date; source published 2025-10-14.
October 9, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.