CB1 and CB2 capacity delivery

Company: TeraWulf

Subject kind
facility timeline
Statement date
2024-12-25
Promised by
2025-06-30
Current status
outcome unconfirmed

What the later record shows

Partly delivered · new target March 31, 2026

Both buildings missed the Q1/Q2 2025 guidance. CB-1 only began recording revenue in mid-August 2025, and CB-2 moved to Q4 2025 and then to Q1 2026. As of February 2026, CB-1 and CB-2A (21 MW) were delivered, while CB-2B (21 MW) was still expected in Q1 2026.

“CB - 1 will begin recording revenue mid - August x CB - 2 on track for Q4 delivery”
2025-08-13 · terawulf 8-K exhibit (tm2523008d1_ex99-3.htm) View cached copy (2026-10-06)Live source ↗
“Wulf Den & CB-1 delivered (18 MW) ➢ CB-2A delivered (21 MW) ➢ CB-2B: 21 MW expected to be delivered in Q1”
2026-02-26 · Q4 Earnings Update Presentation View cached copy (2026-10-06)Live source ↗Archive.org ↗

Checked October 22, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

TeraWulf guided to deliver capacity from buildings CB1 and CB2 in the first and second quarters of 2025.

Source (primary)

terawulf 8-K exhibit (eh240572111_ex9901.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-22)Live source ↗

Quote: “we've guided to deliver capacity in the first and second quarter of next year. And so, the budgets for CB1 and CB2 are fairly well-defined”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (eh240572111_ex9901.htm)

Quote: “we've guided to deliver capacity in the first and second quarter of next year. And so, the budgets for CB1 and CB2 are fairly well-defined”

View cached copy (2026-10-22)Live source ↗

Record of changes

October 22, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 22, 2026 — outcome unconfirmed