CB-1/CB-2 UPS installation May 2026
Company: TeraWulf - Project: La Lupa
What the later record shows
Outcome not yet confirmed
The Q2 2026 presentation lists CB-1 and CB-2A/2B as delivered capacity, but no passage mentions UPS installation or when it was completed.
“DELIVERED 102 MW ➢ WULF Den (2 MW) ➢ CB - 1 (16 MW) ➢ CB - 2A (21 MW) ➢ CB - 2B (21 MW)”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-10-13)Live source ↗Archive.org ↗
Checked October 13, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
UPS installations for CB-1 and CB-2 are expected to be completed in May 2026.
Source (primary)
Q4 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-13)Live source ↗Archive.org ↗
Quote: “UPS installations for CB-1 and CB-2 are expected to be completed in May”
How we checked this
Checked on October 15, 2026. The cited source supports every part of this claim.
The February 2026 construction update says UPS installations for CB-1 and CB-2 are expected to be completed in May.
Confirmed in the source:
- UPS installations for CB-1 and CB-2 are expected to be completed in May 2026
What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_513c80c486e62e4bdb70115ded3782f5/terawulf/db/2396/23307/pdf/TeraWulf_Q4_2025_Investor_Presentation_%28Feb_2026%29.pdf) in full (28,069 characters, retrieved October 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Q4 Earnings Update Presentation
Quote: “UPS installations for CB-1 and CB-2 are expected to be completed in May”