La Lupa additional 50 MW delivery
Company: TeraWulf
What the later record shows
The date slipped · new target March 31, 2026
HPC capacity at year-end 2025 was only 18 critical IT MW, the same capacity as Wulf Den and CB-1, so the additional 50 MW was not delivered on time. Linking it to CB-2A and CB-2B is an inference from La Lupa's 60 MW Core42 commitment, as 18 + 21 + 21 MW equals 60 MW.
“Wulf Den & CB-1 delivered (18 MW) ➢ CB-2A delivered (21 MW) ➢ CB-2B: 21 MW expected to be delivered in Q1”
2026-02-26 · Q4 Earnings Update Presentation View cached copy (2026-10-13)Live source ↗Archive.org ↗
“As of December 31, 2025 the Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity and had 18 critical IT MW of HPC capacity.”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
“pursuant to which we committed to deliver 60 MW of critical IT load”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked November 6, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
La Lupa has 22.5 MW online, with another 50 MW delivering around year-end subject to tenant fit-out requests.
Source (primary)
Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗
Quote: “La Lupa 22.5 of capacity online and another 50 MW delivering around year-end subject to tenant fit-out requests”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Investor Presentation
Quote: “La Lupa 22.5 of capacity online and another 50 MW delivering around year-end subject to tenant fit-out requests”
delays View 10-K PDF
Quote: “As of December 31, 2025 the Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity and had 18 critical IT MW of HPC capacity.”
delays Q4 Earnings Update Presentation
Quote: “Wulf Den & CB-1 delivered (18 MW) ➢ CB-2A delivered (21 MW) ➢ CB-2B: 21 MW expected to be delivered in Q1”