La Lupa additional 50 MW delivery

Company: TeraWulf

This claim was marked delayed on November 6, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2025-11-10
Promised by
2025-12-31
Promised amount
50.0 MW
Current status
delayed

What the later record shows

The date slipped · new target March 31, 2026

HPC capacity at year-end 2025 was only 18 critical IT MW, the same capacity as Wulf Den and CB-1, so the additional 50 MW was not delivered on time. Linking it to CB-2A and CB-2B is an inference from La Lupa's 60 MW Core42 commitment, as 18 + 21 + 21 MW equals 60 MW.

“Wulf Den & CB-1 delivered (18 MW) ➢ CB-2A delivered (21 MW) ➢ CB-2B: 21 MW expected to be delivered in Q1”
2026-02-26 · Q4 Earnings Update Presentation View cached copy (2026-10-13)Live source ↗Archive.org ↗
“As of December 31, 2025 the Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity and had 18 critical IT MW of HPC capacity.”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
“pursuant to which we committed to deliver 60 MW of critical IT load”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked November 6, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

La Lupa has 22.5 MW online, with another 50 MW delivering around year-end subject to tenant fit-out requests.

Source (primary)

Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗

Quote: “La Lupa 22.5 of capacity online and another 50 MW delivering around year-end subject to tenant fit-out requests”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Investor Presentation

Quote: “La Lupa 22.5 of capacity online and another 50 MW delivering around year-end subject to tenant fit-out requests”

View cached copy (2026-11-06)Live source ↗Archive.org ↗

delays View 10-K PDF

Quote: “As of December 31, 2025 the Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity and had 18 critical IT MW of HPC capacity.”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

delays Q4 Earnings Update Presentation

Quote: “Wulf Den & CB-1 delivered (18 MW) ➢ CB-2A delivered (21 MW) ➢ CB-2B: 21 MW expected to be delivered in Q1”

View cached copy (2026-10-13)Live source ↗Archive.org ↗

Record of changes

November 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 6, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.