Core42 GPU-optimized HPC lease
Company: TeraWulf - Project: La Lupa
The claim, verbatim
La Lupa will deliver 72.5 MW of GPU-optimized capacity with approximately $1.1 billion in contracted revenue over ten years under Core42 leases
Source (primary)
terawulf 8-K exhibit (a_wulfformearningsreleaseq.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-27)Live source ↗
Quote: “Under the Core42 leases, La Lupa will deliver 72.5 MW of GPU-optimized capacity with approximately $1.1 billion in contracted revenue over ten years”
How we checked this
Checked on September 29, 2026. The cited source supports every part of this claim.
The release states that under the Core42 leases, La Lupa will deliver 72.5 MW of GPU-optimized capacity with about $1.1 billion in contracted revenue over ten years.
Confirmed in the source:
- The leases are Core42 leases
- La Lupa will deliver 72.5 MW of GPU-optimized capacity under the Core42 leases
- The Core42 leases carry approximately $1.1 billion in contracted revenue
- The Core42 lease term is ten years
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330125000096/a_wulfformearningsreleaseq.htm) in full (25,617 characters, retrieved September 27, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (a_wulfformearningsreleaseq.htm)
Quote: “Under the Core42 leases, La Lupa will deliver 72.5 MW of GPU-optimized capacity with approximately $1.1 billion in contracted revenue over ten years”