CB-1 20 MW operational Q1 2025
Company: TeraWulf - Project: La Lupa
What the later record shows
Delivered late · happened August 31, 2025
The promise was operation by Q1 2025. The October 2025 second-party opinion says CB-1 began operations in August 2025, about five months late.
“Wulf Den and CB-1 began operations in July and August 2025, respectively, while CB-2 is expected to commence operations in November 2025.”
2025-10-14 · TeraWulf Sustainable Finance Framework Second Party Opinion 2025 View cached copy (2026-09-01)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
CB-1 HPC facility with 20 MW capacity expected to be operational in Q1 2025.
Source (primary)
Nautilus Sale Announcement (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-06)Live source ↗
Quote: “CB-1: 20 MW capacity expected to be operational in Q1 2025”
How we checked this
Checked on October 14, 2026. The cited source supports every part of this claim.
The HPC timeline slide states this directly.
Confirmed in the source:
- The CB-1 HPC facility, with 20 MW capacity, is expected to be operational in Q1 2025
What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2396/23300/pdf/WULF_Nautilus_Sale_Announcement_Deck_%2810-03-24%29vF.pdf) in full (14,394 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Nautilus Sale Announcement
Quote: “CB-1: 20 MW capacity expected to be operational in Q1 2025”
confirms TeraWulf Sustainable Finance Framework Second Party Opinion 2025
Quote: “Wulf Den and CB-1 began operations in July and August 2025, respectively, while CB-2 is expected to commence operations in November 2025.”
confirms Nautilus Sale Announcement
Quote: “CB-1: 20 MW capacity expected to be operational in Q1 2025”