jain.com

WULF Den first revenue Q2 2025

Company: TeraWulf - Project: La Lupa

Subject kind
facility timeline
Statement date
2025-05-08
Promised by
2025-06-30
Promised amount
2.5 MW
Current status
verified

What the later record shows

Delivered late · happened July 31, 2025

The target was first WULF Den revenue in Q2 2025. The August 2025 update says WULF Den began recording revenue in July 2025, just after the quarter ended.

“x WULF Den began recording revenue in July x CB - 1 will begin recording revenue mid - August”
2025-08-13 · terawulf 8-K exhibit (tm2523008d1_ex99-3.htm) View cached copy (2026-10-06)Live source ↗
“The Company commenced HPC leasing operations at the Lake Mariner Data Campus in July 2025”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Targeting first HPC revenue from 2.5 MW WULF Den in Q2 2025.

Source (primary)

Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-06)Live source ↗

Quote: “Q2 2025: 2.5 MW WULF Den”

How we checked this

Checked on October 16, 2026. The cited source supports every part of this claim.

The HPC hosting timeline slide, under 'Targeting 1st Revenue', lists Q2 2025 for the 2.5 MW WULF Den.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2396/23301/pdf/WULF_Q1_2025_Investor_Pres_vF.pdf) in full (23,307 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Investor Presentation

Quote: “Q2 2025: 2.5 MW WULF Den”

View cached copy (2026-10-06)Live source ↗

confirms View 10-K PDF

Quote: “The Company commenced HPC leasing operations at the Lake Mariner Data Campus in July 2025”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms terawulf 8-K exhibit (tm2523008d1_ex99-3.htm)

Quote: “x WULF Den began recording revenue in July x CB - 1 will begin recording revenue mid - August”

View cached copy (2026-10-06)Live source ↗

confirms Investor Presentation

Quote: “Q2 2025: 2.5 MW WULF Den”

View cached copy (2026-10-13)Live source ↗Archive.org ↗

confirms terawulf 8-K exhibit (wulfq12025investorpresvf.htm)

Quote: “Q2 2025: 2.5 MW WULF Den”

View cached copy (2026-10-15)Live source ↗

Record of changes

October 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 7, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-10-06 was the source's retrieval date; source published 2025-05-08.
October 9, 2026 — verified