La Lupa additional 50 MW
Company: TeraWulf - Project: La Lupa
What the later record shows
The date slipped
At 2025-12-31 only 18 critical IT MW of HPC was energized, so the extra 50 MW was not delivered around year-end. By February 2026 the campus had 39 critical IT MW online, and the company acknowledged timing impacts from tenant fit-out enhancements.
“Certain building milestones were sequenced accordingly, and associated timing impacts have been incorporated into the Company’s financial plan.”
2026-02-25 · terawulf 8-K exhibit (a_wulfearningsrelease2026-.htm) View cached copy (2026-09-13)Live source ↗
“As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity and remains on track to deliver additional contracted capacity”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
La Lupa has 22.5 MW online with an additional 50 MW delivering around year-end, subject to tenant fit-out requests.
Source (primary)
Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-06)Live source ↗Archive.org ↗
Quote: “La Lupa 22.5 of capacity online and another 50 MW delivering around year-end subject to tenant fit-out requests”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The presentation says La Lupa has 22.5 MW online and another 50 MW delivering around year-end, subject to tenant fit-out requests.
Confirmed in the source:
- La Lupa has 22.5 MW of capacity online
- An additional 50 MW at La Lupa is delivering around year-end
- The La Lupa delivery timing is subject to tenant fit-out requests
What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2396/23306/pdf/WULF_Q3_2025_Investor_Update_%28Nov_2025%29vF.pdf) in full (31,442 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Investor Presentation
Quote: “La Lupa 22.5 of capacity online and another 50 MW delivering around year-end subject to tenant fit-out requests”
delays View 10-K PDF
Quote: “As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity and remains on track to deliver additional contracted capacity”
delays terawulf 8-K exhibit (a_wulfearningsrelease2026-.htm)
Quote: “Certain building milestones were sequenced accordingly, and associated timing impacts have been incorporated into the Company’s financial plan.”