What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today137 MW2026-03-01Kentucky Facility developed capacity
Contracted a customer is on the hook--
Under construction--
Permitted--
Interconnect approved utility has agreed to deliver--
Interconnect requested in a queue, nothing approved--
Announced a press-release figure232 MW2026-03-01Kentucky Facility capacity expansion target

Claims about this project

2025-12-30 - delayed
Block Mining 160 MW targeting timeline 160.0 MW. Promised by 2025-12-31.
2025-12-30 - delayed
Block Mining current and targeted capacity 160.0 MW. Promised by 2025-12-31.
2026-03-01 - stated
2026-03-01 - stated
Kentucky Facility capacity expansion target 232.0 MW. Promised by 2026-12-31.
2026-03-01 - stated
Kentucky Facility capacity expansion target 232.0 MW. Promised by 2026-12-31.
2026-03-01 - stated
Kentucky Facility capacity expansion target 232.0 MW. Promised by 2026-12-31.
2026-03-01 - stated
Kentucky Facility expansion target 232.0 MW. Promised by 2026-12-31.