Block Mining 160 MW targeting timeline

Company: Riot - Project: Kentucky Facility

Subject kind
facility timeline
Statement date
2025-12-30
Promised by
2025-12-31
Promised amount
160.0 MW
Current status
verified

What the later record shows

Delivered late · happened March 31, 2026

The 10-K filed in March 2026 says the Kentucky Facility 'currently' had about 137 MW, short of the 160 MW year-end 2025 target. The Q1 2026 10-Q reports 162 MW, and its table is as of March 31, 2026. One 10-K table lists 192 MW at December 31, 2025, which conflicts with the 10-K text and the later 162 MW figure, so confidence is medium.

“The Kentucky Facility currently has approximately 137 MW of developed capacity.”
2026-03-01 · Riot 10-K filed 2026-03-02 View cached copy (2026-08-31)Live source ↗
“The Kentucky Facility currently provides 162 MW of developed capacity.”
2026-04-29 · Riot 10-Q filed 2026-04-30 View cached copy (2026-08-31)Live source ↗
“The Kentucky Facility currently provides approximately 192 MW of developed capacity.”
2026-08-09 · Riot 10-Q filed 2026-08-10 View cached copy (2026-08-30)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The Company is targeting to reach approximately 160 MW capacity at Block Mining during the remainder of 2025

Source (primary)

Riot 424B5 filed 2025-12-31 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “we are targeting to reach a total of approximately 160 MW during the remainder of 2025”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The filing's summary states the target of approximately 160 MW during the remainder of 2025. Its Kentucky Facility section gives the same target for the first quarter of 2026, so the filing itself is internally inconsistent on timing.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1167419/000110465925125315/riot-20251230x424b5.htm) in full (151,163 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot 424B5 filed 2025-12-31

Quote: “we are targeting to reach a total of approximately 160 MW during the remainder of 2025”

View cached copy (2026-08-31)Live source ↗

confirms Riot 10-Q filed 2026-08-10

Quote: “The Kentucky Facility currently provides approximately 192 MW of developed capacity.”

View cached copy (2026-08-30)Live source ↗

confirms Riot 10-K filed 2026-03-02

Quote: “The Kentucky Facility currently has approximately 137 MW of developed capacity.”

View cached copy (2026-08-31)Live source ↗

confirms Riot 10-Q filed 2026-04-30

Quote: “The Kentucky Facility currently provides 162 MW of developed capacity.”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.