Kentucky facilities online in 2025

Company: Riot

Subject kind
facility timeline
Statement date
2024-10-29
Promised by
2025-12-31
Current status
verified

What the later record shows

Delivered on time · happened December 31, 2025

Riot planned to grow Kentucky deployed capacity from 2.8 EH/s in January 2025 to 6.5 EH/s by year-end 2025. By December 31, 2025, Kentucky showed 6.4 EH/s deployed and 192 MW developed, up from 60 MW, and both sites are described as operational.

“This will grow total Kentucky deployed hash rate capacity from 2.8 EH/s (January 2025) to 6.5 EH/s (YE 2025), a 131% increase.”
2025-02-23 · riot 8-K exhibit (riot-20250224xex99d2.htm) View cached copy (2026-10-19)Live source ↗
“Kentucky Facility ​ ​ 6.4 ​ ​ 2.4 Combined hash rate, deployed ​ ​ 38.5 ​ ​ 31.5”
2026-03-01 · Riot 10-K filed 2026-03-02 View cached copy (2026-08-31)Live source ↗
“Block Mining consists of two operational sites in Kentucky”
2026-03-01 · Riot 10-K filed 2026-03-02 View cached copy (2026-08-31)Live source ↗

Checked October 25, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The recently acquired Kentucky facilities had been expected to come online in 2024. They are now expected to come online in 2025.

Source (primary)

riot 8-K exhibit (riot-20241030xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗

Quote: “the recently acquired Kentucky facilities, which had previously been anticipated to come online this year and which are now expected to come online in 2025”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms riot 8-K exhibit (riot-20241030xex99d1.htm)

Quote: “the recently acquired Kentucky facilities, which had previously been anticipated to come online this year and which are now expected to come online in 2025”

View cached copy (2026-10-25)Live source ↗

confirms Riot 10-K filed 2026-03-02

Quote: “Kentucky Facility ​ ​ 6.4 ​ ​ 2.4 Combined hash rate, deployed ​ ​ 38.5 ​ ​ 31.5”

View cached copy (2026-08-31)Live source ↗

confirms riot 8-K exhibit (riot-20250224xex99d2.htm)

Quote: “This will grow total Kentucky deployed hash rate capacity from 2.8 EH/s (January 2025) to 6.5 EH/s (YE 2025), a 131% increase.”

View cached copy (2026-10-19)Live source ↗

Record of changes

October 25, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 25, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.