Kentucky Facility capacity expansion target

Company: Riot - Project: Kentucky Facility

Subject kind
facility timeline
Statement date
2026-03-01
Promised by
2026-12-31
Promised amount
232.0 MW
Current status
stated

The claim, verbatim

Targeting Kentucky Facility to reach approximately 232 MW total capacity through remainder of 2026

Source (primary)

Riot 10-K filed 2026-03-02 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “We are targeting the Kentucky Facility to reach a total capacity of approximately 232 MW through the remainder of 2026, with additional expansion anticipated”

How we checked this

Checked on September 16, 2026. The cited source supports every part of this claim.

The filing states this capacity target and timeframe for the Kentucky Facility.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1167419/000110465926022322/riot-20251231x10k.htm) in full (516,452 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot 10-K filed 2026-03-02

Quote: “We are targeting the Kentucky Facility to reach a total capacity of approximately 232 MW through the remainder of 2026, with additional expansion anticipated”

View cached copy (2026-08-31)Live source ↗