Horizon

Project of IREN

Kind
campus
Location
Childress, Texas
County
Childress
State/region
TX
Country
US
Status
partially operational as of October 12, 2026

Where it stands

Horizon 1, a 50 MW (IT) liquid-cooled deployment at Childress, was delivered to and accepted by Microsoft in August 2026. Horizons 2-4, three more 50 MW phases that complete the 200 MW Microsoft contract, are in late-stage construction and targeted for the December 2026 quarter. Early site works have started for Horizons 5-6, with no capacity stated. The separate transition of existing Childress capacity (the former mining site) to AI Cloud is excluded from these figures.

50 MW in service · 150 MW under construction · 200 MW planned

PhaseMWStatusDateSource
Horizon 150operational2026-08-13Delivered Horizon 1 to, and received acceptance from, Microsoft in August 2026. Horizon 1 is the first of four 50MW (IT) liquid-cooled deployments at Childress.
2026-10-12 View cached copy (2026-10-14)Live source ↗
Horizons 2-4150under constructionHorizon 1, the first 50 MW deployment for Microsoft, has been delivered, and three more 50 MW phases are targeted for the December quarter.
2026-09-28 View cached copy (2026-09-29)Live source ↗Archive.org ↗
Horizons 5-6plannedincluding late-stage construction of Horizons 1–4 and early site works for Horizons 5–6 at Childress
2026-10-12 View cached copy (2026-10-14)Live source ↗

Assessed October 18, 2026 from the newest filings, releases and reporting that name this project (newest relied on: October 12, 2026).

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today50 MW2026-09-28Horizon 1 50 MW for Microsoft delivered
Contracted a customer is on the hook150 MW2026-09-28Three more 50 MW Microsoft phases in December quarter
Under construction300 MW2026-05-10Horizon 1 Microsoft handoff
Permitted--
Interconnect approved utility has agreed to deliver--
Interconnect requested in a queue, nothing approved--
Announced a press-release figure200 MW2026-08-31Four 50 MW deployments scheduled at Childress, Texas

Who has claimed this site

Capacity commitments in the order they were announced. A commitment that ended shows why.

2025-11-02
Microsoft Corporation - anchor tenant · 300 MW · 5-year term source

Claims about this project

2025-03-05 - outcome unconfirmed
2025-04-03 - verified
Horizon 1 commissioning at Childress 50.0 MW. Promised by 2025-12-31.
2025-05-05 - delayed
Horizon 1 AI data center commissioning H2 2025 50.0 MW. Promised by 2025-12-31.
2025-05-13 - verified
2025-06-29 - verified
Horizon 1 AI data center delivery at Childress 50.0 MW. Promised by 2025-12-31.
2025-07-06 - stated
2025-07-06 - verified
Childress Horizon 1 delivery Q4 2025 50.0 MW. Promised by 2025-12-31.
2025-11-02 - stated
Microsoft GPU Services contract 9700000000.0 USD. Promised by 2031-12-31.
2025-11-02 - stated
2025-11-02 - stated
2025-11-02 - stated
2026-05-10 - verified
Horizon 1 Microsoft handoff 300.0 MW. Promised by 2026-09-30.
2026-05-10 - stated
Horizons 2-4 delivery. Promised by 2026-12-31.
2026-08-13 - stated
2026-08-20 - stated
Horizons 2-4 deployment delivery. Promised by 2026-12-31.
2026-08-21 - stated
2026-08-21 - stated
2026-08-25 - stated
2026-08-25 - stated
2026-08-27 - stated
2026-08-27 - stated
2026-08-28 - verified
2026-08-28 - stated
Horizons 3 and 4 Q4 2026 delivery target 100.0 MW. Promised by 2026-12-31.
2026-08-28 - stated
2026-08-28 - stated
2026-08-28 - stated
Horizons 2-4 targeted for December quarter 150.0 MW. Promised by 2026-12-31.
2026-08-28 - stated
2026-08-28 - stated
Horizons 2 through 4 delivery target 150.0 MW. Promised by 2026-12-31.
2026-08-29 - stated
2026-08-29 - stated
Horizons 2-4 deployment phases. Promised by 2026-12-31.
2026-08-31 - stated
2026-08-31 - stated
2026-08-31 - stated
2026-08-31 - stated
2026-08-31 - stated
Horizons 2-4 delivery targets. Promised by 2026-12-31.
2026-08-31 - stated
2026-08-31 - stated
2026-08-31 - stated
2026-08-31 - stated
2026-08-31 - stated
2026-08-31 - stated
2026-08-31 - stated
Microsoft Horizon data center deliveries 150.0 MW. Promised by 2026-12-31.
2026-09-04 - stated
Horizons 2-4 Facility Deliveries. Promised by 2026-12-31.
2026-09-04 - stated
2026-09-04 - stated
Horizons 2-4 delivery in Q4 2026. Promised by 2026-12-31.
2026-09-04 - stated
Horizons 2-4 data center deliveries. Promised by 2026-12-31.
2026-09-09 - withdrawn
2026-09-09 - stated
2026-09-09 - stated
Horizons 2-4 Projects. Promised by 2026-12-31.
2026-09-10 - stated
2026-09-10 - stated
2026-09-16 - stated
2026-09-28 - stated
2026-09-28 - stated
2026-09-28 - stated
Horizons 2-4 coming online. Promised by 2026-12-31.

Site intelligence

Analytical estimate. Each site below is located from public records (filings, releases, news, OpenStreetMap) and checked against free satellite imagery; "How we located this site" lists every step and the score it earned. The conclusion is computed from night-time lights, surface heat and year-over-year change, with the dates it rests on. These are hypotheses under active tracking, not legal parcels or an official endorsement.
Childress, Texas, TX
Weak
Childress, TX
34.5197, -100.2068
Approximate address GQ9V+V7 Abington, TX, USA Reverse-geocoded from the candidate centroid; not a permit-confirmed parcel address.
Conclusion so far We have not located the site yet. · confidence 30%
Undetermined: we have not yet located the actual site, only the town or county it is in, so imagery cannot say whether anything is running.
What would change this: A published address, parcel, coordinates or permit for the site itself.
Latest clear imagery: Google 2026-09-29
Newest clear images4 clear image date(s)
Visual view of iren-horizon, 2026-09-29 (Google Earth (wide view))
2026-09-29Google Earth (wide view) · 9.5 m/pixel
Visual view of iren-horizon, 2026-09-29 (Google Earth (close view))
2026-09-29Google Earth (close view) · 0.3 m/pixel
Visual view of iren-horizon, 2026-09-06 (Google Earth (wide view))
2026-09-06Google Earth (wide view) · 9.5 m/pixel
Visual view of iren-horizon, 2026-09-06 (Google Earth (close view))
2026-09-06Google Earth (close view) · 0.3 m/pixel
Grid interconnection Closest 345kV substation is 11.8 mi away. At this distance the project would need to build a new substation on- or near-site to deliver announced load — a viability and schedule signal, not a disqualifier.
How we located this site
5/100 (weak): locality location 5
  1. Initial geocode 2026-09-05
    Childress, Texas, TX → town/county centre, 4 km box -- not the site
  2. Nearest substation (earlier method) 2026-09-05
    re-centred on the nearest high-voltage substation (superseded method)
  3. Starting point (the project's stated locality) 2026-10-19
    Childress, Texas → 34.42645, -100.20400 (locality)
  4. No site-level evidence yet 2026-10-19
    no address, road, landmark or coordinates tie this project to a specific parcel yet -- the town is shown, NOT the site