Horizon 2 built and in commissioning

Company: IREN

Subject kind
facility timeline
Statement date
2026-11-06
Current status
stated

The claim, verbatim

Horizon 2 is built. Power is on at the rack in all three halls, GPUs are racked, fiber is installed, and Dell is commissioning, with one integrated test remaining.

Source (primary)

Microsoft design change delays Iren's data center delivery in Texas (-, news_article)
View cached copy (2026-11-07)Live source ↗Archive.org ↗

Quote: “power's on at the rack in all three halls, the GPUs are racked, the fiber's in, Dell is actually commissioning now. So there's one integrated test there.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Microsoft design change delays Iren's data center delivery in Texas

Quote: “power's on at the rack in all three halls, the GPUs are racked, the fiber's in, Dell is actually commissioning now. So there's one integrated test there.”

View cached copy (2026-11-07)Live source ↗Archive.org ↗