Horizon 1 50MW liquid-cooled AI data center delivery in Q4 2025

Company: IREN - Project: Horizon

Subject kind
facility timeline
Statement date
2025-05-13
Promised by
2025-12-31
Promised amount
50.0 MW
Current status
verified

What the later record shows

Delivered late · happened August 13, 2026

The FY26 10-K states Horizon 1 was delivered to and accepted by Microsoft in August 2026, and a news headline dates the delivery to August 13, 2026. That is after the Q4 2025 target.

“Aug 13, 2026 IREN Delivers Horizon 1 to Microsoft and Achieves NVIDIA Exemplar Cloud Status on GB300 NVL72”
2026-08-18 · IREN (NASDAQ: IREN) pays for Mirantis with new shares - Stock Titan View cached copy (2026-08-31)Live source ↗
“Horizon 1 was delivered to, and accepted by, Microsoft in August 2026.”
2026-08-26 · IREN 10-K filed 2026-08-27 View cached copy (2026-08-30)Live source ↗

Checked October 15, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

IREN targets delivery of Horizon 1 at Childress, with up to 50MW (IT load) of liquid-cooled AI data center capacity, in Q4 2025.

Source (primary)

iren 8-K exhibit (q3fy25presentationvf.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-15)Live source ↗

Quote: “Horizon 1 - Up to 50MW (IT load) liquid-cooled capacity targeting Q4 2025 delivery”

How we checked this

Checked on October 17, 2026. The cited source supports every part of this claim.

The highlights slide gives the up-to-50MW liquid-cooled capacity and the Q4 2025 delivery target. The Horizon 1 slide identifies the project as being at Childress and shows Q4 2025 as the 'Data Center Delivered' milestone.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000187884825000043/q3fy25presentationvf.htm) in full (46,276 characters, retrieved October 15, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms iren 8-K exhibit (q3fy25presentationvf.htm)

Quote: “Horizon 1 - Up to 50MW (IT load) liquid-cooled capacity targeting Q4 2025 delivery”

View cached copy (2026-10-15)Live source ↗

confirms iren 8-K exhibit (q3fy25resultspressreleas.htm)

Quote: “Up to 50MW (IT Load) ... Targeting Q4 2025 delivery”

View cached copy (2026-10-15)Live source ↗

confirms IREN 10-K filed 2026-08-27

Quote: “Horizon 1 was delivered to, and accepted by, Microsoft in August 2026.”

View cached copy (2026-08-30)Live source ↗

confirms IREN (NASDAQ: IREN) pays for Mirantis with new shares - Stock Titan

Quote: “Aug 13, 2026 IREN Delivers Horizon 1 to Microsoft and Achieves NVIDIA Exemplar Cloud Status on GB300 NVL72”

View cached copy (2026-08-31)Live source ↗

Record of changes

October 15, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 15, 2026 — verified