Horizon data center combined IT load
Company: IREN - Project: Horizon
The claim, verbatim
Four Horizon data center facilities in Childress will have a combined IT load of approximately 200MW
Source (primary)
IREN 8-K filed 2025-11-03 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “representing a combined IT load of approximately 200MW”
How we checked this
Checked on September 16, 2026. The cited source supports every part of this claim.
The filing names the four Horizon facilities at Childress and states they represent a combined IT load of approximately 200MW.
Confirmed in the source:
- The GPU Services will be installed across four data center facilities at Childress known as Horizon 1, Horizon 2, Horizon 3 and Horizon 4
- Those four facilities represent a combined IT load of approximately 200MW
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1878848/000114036125040072/ef20058139_8k.htm) in full (7,303 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms IREN 8-K filed 2025-11-03
Quote: “representing a combined IT load of approximately 200MW”