Horizon 1 AI data center commissioning H2 2025

Company: IREN - Project: Horizon

This claim was marked delayed on October 16, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2025-05-05
Promised by
2025-12-31
Promised amount
50.0 MW
Current status
delayed

What the later record shows

The date slipped · new target December 31, 2026

No passage says Horizon 1 was commissioned in H2 2025. In May 2026, IREN said Horizons 1-4 were on track for delivery by year-end 2026, which implies Horizon 1 had not yet been delivered.

“Childress Horizon 1 (Texas, USA) 75 N/A Under construction”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗
“2026 expansion to 480MW on track o Horizon 1-4 on track for delivery by year-end”
2026-05-07 · iren 8-K exhibit (irenreportsq3fy26results.htm) View cached copy (2026-09-08)Live source ↗

Checked October 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Horizon 1, a 50MW IT load liquid-cooled AI data center at Childress, is on track for commissioning/delivery in H2 2025.

Source (primary)

iren 8-K exhibit (aprilmonthlyupdatevf.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-16)Live source ↗

Quote: “Horizon 1 (50MW IT load) on track for H2 2025 commissioning”

How we checked this

Checked on October 17, 2026. The cited source supports every part of this claim.

The update calls Horizon 1 a 50MW IT load AI data center at Childress on track for H2 2025. Management presents it as IREN's liquid-cooled capacity for Blackwell GPUs.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000187884825000037/aprilmonthlyupdatevf.htm) in full (21,129 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms iren 8-K exhibit (aprilmonthlyupdatevf.htm)

Quote: “Horizon 1 (50MW IT load) on track for H2 2025 commissioning”

View cached copy (2026-10-16)Live source ↗

delays IREN 10-K filed 2025-08-28

Quote: “Childress Horizon 1 (Texas, USA) 75 N/A Under construction”

View cached copy (2026-08-31)Live source ↗

delays iren 8-K exhibit (irenreportsq3fy26results.htm)

Quote: “2026 expansion to 480MW on track o Horizon 1-4 on track for delivery by year-end”

View cached copy (2026-09-08)Live source ↗

Record of changes

October 16, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 16, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.