jain.com

Horizon 1 handed over to Microsoft; built in 14 months

Company: IREN

Subject kind
facility timeline
Statement date
2026-11-06
Current status
stated

The claim, verbatim

IREN has handed Horizon 1 over to Microsoft. It delivered Horizon 1 from civil works to a validated GB300 cluster in 14 months.

Source (primary)

Microsoft design change delays Iren's data center delivery in Texas (-, news_article)
View cached copy (2026-11-07)Live source ↗Archive.org ↗

Quote: “the company has been able to deliver Horizon 1 from civils to a validated GB300 cluster in 14 months”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Microsoft design change delays Iren's data center delivery in Texas

Quote: “the company has been able to deliver Horizon 1 from civils to a validated GB300 cluster in 14 months”

View cached copy (2026-11-07)Live source ↗Archive.org ↗