Microsoft GPU Services contract
Company: IREN - Project: Horizon
The claim, verbatim
IE US Hardware 3 entered into a Partner Statement of Work with Microsoft to provide dedicated GPU infrastructure capacity at Horizon data center facilities in Childress, Texas over a five-year average term with total contract value of approximately $9.7 billion through 2031
Source (primary)
IREN 8-K filed 2025-11-03 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “IE US Hardware 3 will provide Microsoft access to dedicated GPU infrastructure capacity in tranches (each, a "GPU Service") at "Horizon" data center facilities located in Childress, Texas over a five-year average term. The total contract value is approximately $9.7 billion through 2031”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms IREN 8-K filed 2025-11-03
Quote: “IE US Hardware 3 will provide Microsoft access to dedicated GPU infrastructure capacity in tranches (each, a "GPU Service") at "Horizon" data center facilities located in Childress, Texas over a five-year average term. The total contract value is approximately $9.7 billion through 2031”