ARR delay could extend to end of February

Company: IREN

Subject kind
facility timeline
Statement date
2026-11-05
Promised by
2027-02-28
Promised amount
4000000000.0 USD
Current status
stated

The claim, verbatim

If suppliers are late, completion of commissioning and the ARR target may run to the end of February 2027.

Source (primary)

Microsoft design change delays Iren's data center delivery in Texas (-, news_article)
View cached copy (2026-11-07)Live source ↗Archive.org ↗

Quote: “If they're late, as suppliers have been across the industry this year, it may run to the end of February.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Microsoft design change delays Iren's data center delivery in Texas

Quote: “If they're late, as suppliers have been across the industry this year, it may run to the end of February.”

View cached copy (2026-11-07)Live source ↗Archive.org ↗