Stingray Facility
Project of Cipher Mining
Where it stands
Stingray is a wholly-owned 100 gross MW / 70 IT MW HPC data center in Andrews, Texas, fully leased to Amazon Data Services, with rent targeted to start April–May 2027. Cipher closed an $810 million 6% bond offering in June 2026 to finance the remaining construction cost. No passage reports any capacity energized or in service yet. Stingray should not be confused with the Bear and Chief joint-venture mining facilities, which are also near Andrews.
100 MW under construction · 100 MW planned
| Phase | MW | Status | Date | Source |
|---|---|---|---|---|
| Network Hall (10 IT MW) | 10 | under construction | 2027-04-01 | 10 IT MW Network Hall Target Rent Commencement Date of April 1, 2027; 60 IT MW Data Hall Target Rent Commencement Date of May 1, 2027 2026-06-07 View cached copy (2026-09-06)Live source ↗ |
| Data Hall (60 IT MW) | 60 | under construction | 2027-05-01 | 10 IT MW Network Hall Target Rent Commencement Date of April 1, 2027; 60 IT MW Data Hall Target Rent Commencement Date of May 1, 2027 2026-06-07 View cached copy (2026-09-06)Live source ↗ |
Assessed October 18, 2026 from the newest filings, releases and reporting that name this project (newest relied on: September 8, 2026).
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | -- | ||
| Contracted a customer is on the hook | 70 MW IT load | 2026-06-07 | Stingray critical IT load capacity |
| Under construction | -- | ||
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | 100 MW | 2026-02-23 | Stingray 100 MW facility Q4 2026 energization |
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 100 MW | 2025-11-02 | Stingray 100 MW facility |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
Claims about this project
Site intelligence
How we located this site
- Initial geocode 2026-09-05
Andrews, Texas, TX → town/county centre, 4 km box -- not the site - Nearest substation (earlier method) 2026-09-05
re-centred on the nearest high-voltage substation (superseded method) - Starting point (the project's stated locality) 2026-10-19
Andrews, Texas → 32.31872, -102.54572 (locality) - No site-level evidence yet 2026-10-19
no address, road, landmark or coordinates tie this project to a specific parcel yet -- the town is shown, NOT the site - OpenStreetMap features nearby 2026-10-19