AWS construction cost overrun coverage
Company: Cipher Mining - Project: Stingray Facility
The claim, verbatim
AWS agrees to cover any Stingray construction cost overruns above $10.5 million per IT MW
Source (primary)
cipher-mining 8-K exhibit (dp248110_ex9901.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-06)Live source ↗
Quote: “Amazon agrees to cover any construction cost overruns above $10.5MM/IT MW”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms cipher-mining 8-K exhibit (dp248110_ex9901.htm)
Quote: “Amazon agrees to cover any construction cost overruns above $10.5MM/IT MW”