Stingray Q4 2026 substation energization target
Company: Cipher Mining - Project: Stingray Facility
What the later record shows
Outcome not yet confirmed
No passage reports the status of the Stingray substation electrical work or Q4 2026 energization.
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Stingray substation electrical work is targeted to align with Q4 2026 energization timeline.
Source (primary)
cipher-mining 8-K exhibit (exh992cipherdigital_busi.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-08)Live source ↗
Quote: “Electrical work for substation has commenced, aligning with Q4 2026 target energization timeline”
How we checked this
Checked on October 3, 2026. The cited source supports every part of this claim.
The Stingray construction update in this presentation says electrical work for the substation has commenced, aligning with a Q4 2026 target energization timeline, which matches the claim.
Confirmed in the source:
- Cipher Digital's May 5, 2026 business update states that electrical work for the Stingray substation has commenced.
- The same update states this substation work aligns with a Q4 2026 target energization timeline for Stingray.
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000181998926000025/exh992cipherdigital_busi.htm) in full (22,565 characters, retrieved September 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms cipher-mining 8-K exhibit (exh992cipherdigital_busi.htm)
Quote: “Electrical work for substation has commenced, aligning with Q4 2026 target energization timeline”