Stingray energization Q2 2026
Company: Cipher Mining
What the later record shows
Outcome not yet confirmed
Updates in mid-2025 pushed Stingray energization to Q3 2026. The February 2026 10-K then said first half of 2026. No later passage confirms energization, and the June 2026 AWS lease targets rent starting April 2027.
“100 MW Approved Power Capacity 250 Acres Total Acreage • Energization expected in Q3 2026”
2025-08-06 · cipher-mining 8-K exhibit (ciphermining_businessupd.htm) View cached copy (2026-10-08)Live source ↗
“The Stingray Site has conditional ERCOT interconnection approval of up to 100 MW. We expect to energize the site in the first half of 2026.”
2026-02-23 · Cipher Mining 10-K filed 2026-02-24 View cached copy (2026-08-31)Live source ↗
“Purpose - built HPC data center located in Andrews, TX with 70 MW of Critical IT load under contract, with initial rent targeted t o start on April 1 st , 2027”
2026-06-07 · cipher-mining 8-K exhibit (dp248110_ex9901.htm) View cached copy (2026-09-06)Live source ↗
Checked October 19, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Cipher expects the Stingray site, with 100 MW of approved interconnection, to energize in Q2 2026.
Source (primary)
cipher-mining 8-K exhibit (exh992revduploadtoworkiv.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-19)Live source ↗
Quote: “Expected to energize Q2 2026”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms cipher-mining 8-K exhibit (exh992revduploadtoworkiv.htm)
Quote: “Expected to energize Q2 2026”