Stingray 100 MW energization 3Q 2026
Company: Cipher Mining - Project: Stingray Facility
What the later record shows
Outcome not yet confirmed
The 10-K moved the energization expectation to 1H 2026, which is only a forecast. The August 2026 update covers construction progress, and no passage says the Stingray site was actually energized.
“The Stingray Site has conditional ERCOT interconnection approval of up to 100 MW. We expect to energize the site in the first half of 2026.”
2026-02-23 · Cipher Mining 10-K filed 2026-02-24 View cached copy (2026-08-31)Live source ↗
“Earthwork, grading, and pad preparation progressing on schedule and underground electrical work has commenced”
2026-08-03 · cipher-mining 8-K exhibit (cipherdigital_businessup.htm) View cached copy (2026-09-02)Live source ↗
Checked October 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The Stingray site (100 MW approved capacity, 250 owned acres in West Texas) is expected to be energized in 3Q 2026.
Source (primary)
cipher-mining 8-K exhibit (exh992ciphermining_busin.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-16)Live source ↗
Quote: “Energization expected in 3Q 2026”
How we checked this
Checked on October 17, 2026. The cited source supports every part of this claim.
The Stingray slide states each of these facts.
Confirmed in the source:
- Stingray has 100 MW of approved power capacity
- Stingray comprises 250 acres of owned land in West Texas
- Stingray energization is expected in 3Q 2026
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000181998925000034/exh992ciphermining_busin.htm) in full (18,992 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms cipher-mining 8-K exhibit (exh992ciphermining_busin.htm)
Quote: “Energization expected in 3Q 2026”