Stingray energization Q3 2026
Company: Cipher Mining - Project: Stingray Facility
What the later record shows
Outcome not yet confirmed
No passage says whether Stingray was energized in Q3 2026 or that the target moved. Later passages cover only financing and the 2027 lease rent start dates.
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Stingray site (100 MW approved) is expected to be energized in Q3 2026; substation development has begun and long-lead items including transformers and HV breakers are secured.
Source (primary)
cipher-mining 8-K exhibit (ciphermining_businessupd.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-08)Live source ↗
Quote: “Energization expected in Q3 2026 • Initiated development of substation and secured long-lead items including transformers and high-voltage breakers”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The Stingray slide states each of these points.
Confirmed in the source:
- The Stingray site has 100 MW of approved power capacity
- Stingray energization is expected in Q3 2026
- Cipher has initiated development of a substation at Stingray
- Cipher has secured long-lead items for Stingray, including transformers and high-voltage breakers
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000181998925000079/ciphermining_businessupd.htm) in full (19,841 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms cipher-mining 8-K exhibit (ciphermining_businessupd.htm)
Quote: “Energization expected in Q3 2026 • Initiated development of substation and secured long-lead items including transformers and high-voltage breakers”