Stingray site energization
Company: Cipher Mining - Project: Stingray Facility
What the later record shows
The date slipped · new target September 30, 2026
In August 2025 the company's business update moved the Stingray energization target from H1 2026 to Q3 2026. No later passage confirms that energization happened.
“Stingray 2026 GROWTH 100 MW Approved Power Capacity 250 Acres Total Acreage • Energization expected in Q3 2026”
2025-08-06 · cipher-mining 8-K exhibit (ciphermining_businessupd.htm) View cached copy (2026-10-08)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Expect to energize Stingray site in H1 2026
Source (primary)
Cipher Mining 10-K filed 2025-02-25 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “We expect to energize the site in the first half of 2026”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The 10-K's Stingray Site section states the company expects to energize the site in the first half of 2026.
Confirmed in the source:
- Cipher expects to energize the Stingray Site in the first half of 2026
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1819989/000181998925000005/cifr-20241231.htm) in full (492,885 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Cipher Mining 10-K filed 2025-02-25
Quote: “We expect to energize the site in the first half of 2026”
delays cipher-mining 8-K exhibit (ciphermining_businessupd.htm)
Quote: “Stingray 2026 GROWTH 100 MW Approved Power Capacity 250 Acres Total Acreage • Energization expected in Q3 2026”