MTL-3
Project of WhiteFiber
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | -- | ||
| Contracted a customer is on the hook | 7 MW | 2026-03-25 | MTL-3 lease for 7 MW facility |
| Under construction | 7 MW | 2025-07-28 | MTL-3 data center site secured |
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 7 MW | 2026-03-25 | MTL-3 lease and development commitment |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
2025-07-10
Cerebras Wafer Scale ULC Systems - tenant · 5 MW · 5-year term source
Claims about this project
2025-07-10 - delayed
MTL-3 completion and revenue start. Promised by 2026-01-31.
2025-07-10 - stated
Cerebras colocation agreement 5.0 MW.
2025-07-10 - stated
MTL-3 Saint-Jérôme data center 7.0 MW.
2025-07-22 - stated
2025-07-22 - stated
Cerebras colocation agreement 5.0 MW.
2025-07-28 - delayed
2025-07-28 - delayed
MTL-3 completion timeline. Promised by 2025-12-31.
2025-07-28 - stated
2025-07-31 - stated
2025-07-31 - delayed
MTL-3 operational completion. Promised by 2025-12-31.
2025-07-31 - stated
Cerebras colocation agreement 5.0 MW.
2025-08-07 - delayed
MTL-3 completion timeline. Promised by 2025-12-31.
2025-08-07 - stated
Cerebras colocation agreement 5.0 MW.
2026-03-25 - stated
Cerebras monthly billing at MTL-3 979000.0 USD.
2026-03-25 - stated
Cerebras contract at MTL-3 979.0 USD/month.
2026-03-25 - stated
2026-03-25 - stated
MTL-3 lease for 7 MW facility 7.0 MW.
2026-03-25 - stated
Cerebras MTL-3 contract 58740000.0 USD.
2026-03-25 - stated
2026-03-25 - delayed
2026-03-25 - delayed
2026-03-25 - delayed