MTL-3

Project of WhiteFiber

Kind
datacenter
Location
Saint-Jerome, Quebec
State/region
Quebec
Country
CA
Status
announced

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today--
Contracted a customer is on the hook7 MW2026-03-25MTL-3 lease for 7 MW facility
Under construction7 MW2025-07-28MTL-3 data center site secured
Permitted--
Interconnect approved utility has agreed to deliver--
Interconnect requested in a queue, nothing approved--
Announced a press-release figure7 MW2026-03-25MTL-3 lease and development commitment

Who has claimed this site

Capacity commitments in the order they were announced. A commitment that ended shows why.

2025-07-10
Cerebras Wafer Scale ULC Systems - tenant · 5 MW · 5-year term source

Claims about this project

2025-07-10 - delayed
MTL-3 completion and revenue start. Promised by 2026-01-31.
2025-07-10 - stated
2025-07-10 - stated
2025-07-22 - stated
2025-07-22 - stated
2025-07-28 - delayed
MTL-3 data center site secured 7.0 MW. Promised by 2025-04-11.
2025-07-28 - delayed
MTL-3 completion timeline. Promised by 2025-12-31.
2025-07-28 - stated
2025-07-31 - stated
2025-07-31 - delayed
MTL-3 operational completion. Promised by 2025-12-31.
2025-07-31 - stated
2025-08-07 - delayed
MTL-3 completion timeline. Promised by 2025-12-31.
2025-08-07 - stated
2026-03-25 - stated
2026-03-25 - stated
2026-03-25 - stated
2026-03-25 - stated
2026-03-25 - stated
Cerebras MTL-3 contract 58740000.0 USD.
2026-03-25 - stated
2026-03-25 - delayed
MTL-3 purchase option exercise and closing 17.3 USD. Promised by 2026-06-30.
2026-03-25 - delayed
MTL-3 facility lease and purchase option exercised 17.3 USD. Promised by 2026-06-30.
2026-03-25 - delayed
MTL-3 purchase option exercise and close 17300000.0 USD. Promised by 2026-06-30.