MTL-3 lease and development commitment

Company: WhiteFiber - Project: MTL-3

Subject kind
facility capacity
Statement date
2026-03-25
Promised amount
7.0 MW
Current status
stated

The claim, verbatim

Leased data center site in Saint-Jerome, Quebec to develop into 7 MW Tier-3 facility; 5 MW committed to Cerebras customer

Source (primary)

WhiteFiber 10-K filed 2026-03-26 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “On April 11, 2025, we entered into a lease for a new data center site in Saint-Jerome, Quebec...MTL-3...being developed into a 7 MW (gross) Tier-3 data center. It will support current contracted capacity, with Cerebras (5 MW IT Load)”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms WhiteFiber 10-K filed 2026-03-26

Quote: “On April 11, 2025, we entered into a lease for a new data center site in Saint-Jerome, Quebec...MTL-3...being developed into a 7 MW (gross) Tier-3 data center. It will support current contracted capacity, with Cerebras (5 MW IT Load)”

View cached copy (2026-08-31)Live source ↗