Muskogee
Project of Core Scientific
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | 100 MW | 2026-03-01 | Muskogee, Oklahoma facility |
| Contracted a customer is on the hook | 440 MW | 2026-05-05 | Electrical capacity at Muskogee facility |
| Under construction | 100 MW | 2026-09-01 | Muskogee OK facility capacity in development |
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 1,500 MW | 2026-08-31 | Muskogee campus power expansion |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
2026-07-27
Advanced Micro Devices - tenant · 15-year term source
Claims about this project
2024-11-05 - stated
2026-03-01 - stated
Muskogee, Oklahoma facility 100.0 MW.
2026-05-05 - stated
Acquisition deposit 120.0 USD.
2026-05-05 - stated
Acquisition of land at Muskogee facility 40.0 acres.
2026-05-05 - stated
Electrical capacity at Muskogee facility 440.0 MW.
2026-05-05 - stated
2026-05-05 - stated
Post-acquisition lease termination date. Promised by 2028-06-30.
2026-05-05 - stated
Acquisition purchase price 421.0 USD.
2026-08-13 - stated
2026-08-13 - stated
Polaris DS LLC acquisition purchase price 444300000.0 USD.
2026-08-31 - stated
Muskogee campus power expansion 1.5 GW.
2026-08-31 - stated
2026-09-01 - delayed
2026-09-01 - stated
Muskogee OK site delivery. Promised by 2027-12-31.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
Muskogee billable power capacity 70.0 MW.
2026-09-01 - stated
Muskogee OK site target 70 MW 70.0 MW.
2026-09-01 - stated
Polaris Muskogee power delivery. Promised by 2027-10-31.