Muskogee

Project of Core Scientific

Kind
datacenter
Location
Muskogee, Oklahoma
County
Muskogee County
State/region
OK
Country
US
Status
announced

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today100 MW2026-03-01Muskogee, Oklahoma facility
Contracted a customer is on the hook440 MW2026-05-05Electrical capacity at Muskogee facility
Under construction100 MW2026-09-01Muskogee OK facility capacity in development
Permitted--
Interconnect approved utility has agreed to deliver--
Interconnect requested in a queue, nothing approved--
Announced a press-release figure1,500 MW2026-08-31Muskogee campus power expansion

Who has claimed this site

Capacity commitments in the order they were announced. A commitment that ended shows why.

2026-07-27
Advanced Micro Devices - tenant · 15-year term source
2026-09-01
CoreWeave - tenant · 70 MW source

Claims about this project

2026-03-01 - stated
2026-05-05 - stated
2026-05-05 - stated
2026-05-05 - stated
2026-05-05 - stated
Contingent acquisition payment 40.0 USD. Promised by 2026-12-31.
2026-05-05 - stated
2026-05-05 - stated
2026-08-13 - stated
Contingent capacity-based earnout 40.0 MW. Promised by 2026-12-31.
2026-08-13 - stated
2026-08-31 - stated
2026-08-31 - stated
2026-09-01 - delayed
Muskogee, OK CoreWeave facility delivery 70.0 MW. Promised by 2026-06-30.
2026-09-01 - stated
Muskogee OK site delivery. Promised by 2027-12-31.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
Polaris Muskogee power delivery. Promised by 2027-10-31.