Muskogee Polaris initial power delivery

Company: Core Scientific - Project: Muskogee

Subject kind
facility timeline
Statement date
2026-05-06
Promised by
2027-12-31
Promised amount
440.0 MW
Current status
stated

The claim, verbatim

Core Scientific expects initial power delivery at the Polaris site in Muskogee, OK in late 2027. The site has ~440 MW of power tied to the CoreWeave contract.

Source (primary)

First Quarter Fiscal Year 2026 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-10-16)Live source ↗Archive.org ↗

Quote: “Expect initial power delivery in late 2027.”

How we checked this

Checked on October 17, 2026. The cited source supports part of this claim, but not all of it.

The late-2027 initial power delivery is stated. The deck's Muskogee breakdown appears to attribute ~440 MW to the Polaris acquisition and the smaller ~100 MW of current power to the CoreWeave contract, so it does not establish that ~440 MW is tied to CoreWeave.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11271/pdf/Q1+FY26+earnings+deck.pdf) in full (14,811 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms First Quarter Fiscal Year 2026 Earnings Presentation

Quote: “Expect initial power delivery in late 2027.”

View cached copy (2026-10-16)Live source ↗Archive.org ↗