jain.com

Muskogee, Oklahoma facility expected capacity

Company: Core Scientific - Project: Muskogee

Subject kind
facility capacity
Statement date
2022-03-29
Promised amount
500.0 MW
Current status
stated

The claim, verbatim

A 500MW blockchain data center is being developed at the Port of Muskogee John T. Griffin Industrial Park

Source (primary)

Core Scientific 10-K filed 2022-03-30 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “to develop a 500MW data center at the Port of Muskogee John T. Griffin Industrial Park”

How we checked this

Checked on September 22, 2026. The cited source supports every part of this claim.

The document confirms the agreement to develop a 500MW data center at the Port of Muskogee John T. Griffin Industrial Park.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1839341/000119312522088850/d268076d10k.htm) in full (452,768 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Core Scientific 10-K filed 2022-03-30

Quote: “to develop a 500MW data center at the Port of Muskogee John T. Griffin Industrial Park”

View cached copy (2026-09-13)Live source ↗