70 MW Nvidia GB300 building on track for Q2 2026 delivery

Company: Core Scientific - Project: Muskogee

Subject kind
facility timeline
Statement date
2026-05-05
Promised by
2026-06-30
Promised amount
70.0 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

The Q2 2026 earnings deck's CoreWeave status table shows Muskogee's ~70 MW billing as of mid-July 2026, so the building was handed over. No passage says whether that happened by June 30 or in early July. The August 18 news article only repeats the earlier expectation.

“Nearing full completion of the CoreWeave buildout Site MW Leased Status MW Billing”
2026-07-28 · Second Quarter Fiscal Year 2026 Earnings Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
“Muskogee, OK ~70 MW Marble, NC ~65 MW Austin, TX ~20 MW Total ~590 MW Substantially complete Est. completion early 2027 ~260 ~30 ~70 ~65 ~20 Early 2027 completion Over 430 MW* 9 *Total billing as of mid-July”
2026-07-28 · Second Quarter Fiscal Year 2026 Earnings Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Leased 70 megawatt building designed for Nvidia GB300 platform expected for delivery to customer in Q2 2026

Source (primary)

core-scientific 8-K exhibit (exhibit991polarispressre.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-08)Live source ↗

Quote: “Company's current leased 70 MW building designed to support the Nvidia GB300 platform is progressing through final testing as well as commissioning and is on track for a second quarter 2026 delivery to its customer”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The press release states that the leased 70 MW building designed for the Nvidia GB300 platform is in final testing and commissioning and is on track for Q2 2026 delivery to its customer.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1839341/000162828026030918/exhibit991polarispressre.htm) in full (7,367 characters, retrieved September 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms core-scientific 8-K exhibit (exhibit991polarispressre.htm)

Quote: “Company's current leased 70 MW building designed to support the Nvidia GB300 platform is progressing through final testing as well as commissioning and is on track for a second quarter 2026 delivery to its customer”

View cached copy (2026-09-08)Live source ↗

confirms Second Quarter Fiscal Year 2026 Earnings Presentation

Quote: “Nearing full completion of the CoreWeave buildout Site MW Leased Status MW Billing”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

September 8, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 9, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.