Muskogee, OK CoreWeave facility delivery
Company: Core Scientific - Project: Muskogee
What the later record shows
Delivered; the record does not say when
The Q2 2026 deck shows ~70 MW billing at Muskogee as of mid-July 2026, indicating the CoreWeave facility was delivered. It does not say whether delivery happened by June 30.
“Nearing full completion of the CoreWeave buildout Site MW Leased Status MW Billing”
2026-07-28 · Second Quarter Fiscal Year 2026 Earnings Presentation View cached copy (2026-09-26)Live source ↗
“Muskogee, OK ~70 MW Marble, NC ~65 MW Austin, TX ~20 MW Total ~590 MW Substantially complete Est. completion early 2027 ~260 ~30 ~70 ~65 ~20 Early 2027 completion Over 430 MW* 9 *Total billing as of mid-July”
2026-07-28 · Second Quarter Fiscal Year 2026 Earnings Presentation View cached copy (2026-09-26)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Muskogee, Oklahoma CoreWeave facility with approximately 70 megawatts leased power on track for midyear 2026 delivery
Source (primary)
First Quarter Fiscal Year 2026 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗Archive.org ↗
Quote: “Muskogee, OK Leased power: ~70MW On track for midyear delivery”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The CoreWeave slide lists Muskogee, OK with ~70MW of leased power and says it is on track for midyear delivery. Given the deck's May 2026 date, midyear refers to 2026.
Confirmed in the source:
- Muskogee, Oklahoma is one of the sites where CoreWeave is contracted for leased customer power capacity
- The Muskogee, Oklahoma CoreWeave site has approximately 70 MW of leased power
- The Muskogee, Oklahoma site was on track for midyear delivery, in a deck dated May 6, 2026
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_eb9c314ac28438fbd39d12d91c4e5bdc/corescientific/db/1066/11271/pdf/Q1+FY26+earnings+deck.pdf) in full (14,811 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms First Quarter Fiscal Year 2026 Earnings Presentation
Quote: “Muskogee, OK Leased power: ~70MW On track for midyear delivery”
confirms First Quarter Fiscal Year 2026 Earnings Presentation
Quote: “Muskogee, OK Leased power: ~70MW On track for midyear delivery”
confirms Second Quarter Fiscal Year 2026 Earnings Presentation
Quote: “Nearing full completion of the CoreWeave buildout Site MW Leased Status MW Billing”