Muskogee, OK CoreWeave facility delivery

Company: Core Scientific - Project: Muskogee

Subject kind
facility timeline
Statement date
2026-05-06
Promised by
2026-06-30
Promised amount
70.0 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

The Q2 2026 deck shows ~70 MW billing at Muskogee as of mid-July 2026, indicating the CoreWeave facility was delivered. It does not say whether delivery happened by June 30.

“Nearing full completion of the CoreWeave buildout Site MW Leased Status MW Billing”
2026-07-28 · Second Quarter Fiscal Year 2026 Earnings Presentation View cached copy (2026-09-26)Live source ↗
“Muskogee, OK ~70 MW Marble, NC ~65 MW Austin, TX ~20 MW Total ~590 MW Substantially complete Est. completion early 2027 ~260 ~30 ~70 ~65 ~20 Early 2027 completion Over 430 MW* 9 *Total billing as of mid-July”
2026-07-28 · Second Quarter Fiscal Year 2026 Earnings Presentation View cached copy (2026-09-26)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Muskogee, Oklahoma CoreWeave facility with approximately 70 megawatts leased power on track for midyear 2026 delivery

Source (primary)

First Quarter Fiscal Year 2026 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “Muskogee, OK Leased power: ~70MW On track for midyear delivery”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The CoreWeave slide lists Muskogee, OK with ~70MW of leased power and says it is on track for midyear delivery. Given the deck's May 2026 date, midyear refers to 2026.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_eb9c314ac28438fbd39d12d91c4e5bdc/corescientific/db/1066/11271/pdf/Q1+FY26+earnings+deck.pdf) in full (14,811 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms First Quarter Fiscal Year 2026 Earnings Presentation

Quote: “Muskogee, OK Leased power: ~70MW On track for midyear delivery”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms First Quarter Fiscal Year 2026 Earnings Presentation

Quote: “Muskogee, OK Leased power: ~70MW On track for midyear delivery”

View cached copy (2026-09-26)Live source ↗Archive.org ↗

confirms Second Quarter Fiscal Year 2026 Earnings Presentation

Quote: “Nearing full completion of the CoreWeave buildout Site MW Leased Status MW Billing”

View cached copy (2026-09-26)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2026-05-06.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.