Dalton 1
Project of Core Scientific
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | 195 MW | 2026-03-01 | Dalton, Georgia facility |
| Contracted a customer is on the hook | 175 MW | 2026-09-01 | Dalton, GA CoreWeave facility completion |
| Under construction | -- | ||
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 175 MW | 2026-09-01 | Dalton GA site target 175 MW |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
Claims about this project
2026-03-01 - stated
Dalton, Georgia facility 195.0 MW.
2026-03-30 - stated
2026-09-01 - stated
Dalton 1 GA facility capacity 50.0 MW.
2026-09-01 - stated
Dalton billable power capacity 70.0 MW.
2026-09-01 - stated
Dalton GA site target 175 MW 175.0 MW.
2026-09-01 - stated
2026-09-01 - stated
Dalton GA site delivery. Promised by 2027-12-31.