Dalton, GA full completion for CoreWeave
Company: Core Scientific
The claim, verbatim
Phase 1 (30 MW) at Dalton, GA has been delivered; full completion of the ~175 MW site is on track for early 2027.
Source (primary)
First Quarter Fiscal Year 2026 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-11-11)Live source ↗Archive.org ↗
Quote: “Dalton, GA Leased power: ~175MW Delivered Phase 1, a 30 MW site. Full completion on track for early 2027”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms First Quarter Fiscal Year 2026 Earnings Presentation
Quote: “Dalton, GA Leased power: ~175MW Delivered Phase 1, a 30 MW site. Full completion on track for early 2027”