Dalton campus: ~175 MW leased to CoreWeave, ~30 MW billing in July
Company: Core Scientific - Project: Dalton 1
The claim, verbatim
In its July earnings presentation, Core Scientific showed about 30 MW billing at the Dalton campus against roughly 175 MW leased to CoreWeave.
Source (primary)
Core Scientific’s Billing AI Data Center Capacity Rises to 485 MW - TheEnergyMag (-, news_article)
View cached copy (2026-10-14)Live source ↗Archive.org ↗
Quote: “Core Scientific showed about 30 MW billing at the Georgia campus against roughly 175 MW leased to the cloud computing provider”
How we checked this
Checked on October 16, 2026. The cited source supports every part of this claim.
The article says the July earnings presentation showed about 30 MW billing at the Georgia (Dalton) campus against roughly 175 MW leased to CoreWeave.
Confirmed in the source:
- Core Scientific's July earnings presentation showed about 30 MW billing at the Dalton, Georgia campus
- About 175 MW at the Dalton campus was leased to CoreWeave
What we did: Read our cached copy of the publisher (https://www.theenergymag.com/news/market-news/core-scientific-ai-billing-485-megawatt) in full (3,242 characters, retrieved October 14, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Core Scientific’s Billing AI Data Center Capacity Rises to 485 MW - TheEnergyMag
Quote: “Core Scientific showed about 30 MW billing at the Georgia campus against roughly 175 MW leased to the cloud computing provider”