jain.com

Dalton, GA full completion

Company: Core Scientific - Project: Dalton 1

Subject kind
facility timeline
Statement date
2026-05-06
Promised by
2027-03-31
Promised amount
175.0 MW
Current status
stated

The claim, verbatim

Full completion of the ~175 MW Dalton, GA site is on track for early 2027.

Source (primary)

First Quarter Fiscal Year 2026 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-10-16)Live source ↗Archive.org ↗

Quote: “Full completion on track for early 2027”

How we checked this

Checked on October 17, 2026. The cited source supports every part of this claim.

The deck lists Dalton, GA at ~175 MW leased power with full completion on track for early 2027.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11271/pdf/Q1+FY26+earnings+deck.pdf) in full (14,811 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms First Quarter Fiscal Year 2026 Earnings Presentation

Quote: “Full completion on track for early 2027”

View cached copy (2026-10-16)Live source ↗Archive.org ↗