Vega

Project of Hut 8

Kind
mining
Status
operational as of August 14, 2026

Where it stands

Hut 8 completed initial energization of its 205 MW, single-building Vega ASIC compute facility near Amarillo, Texas in June 2025, and miner energization finished in June and July 2025. American Bitcoin bought the hosted Bitmain miners in August 2025 and began mining there, and Q2 2026 filings and the earnings call still credit Vega with operating capacity. No passage reports added capacity under construction at Vega; an analyst note in P43 mentions 'execution' on Vega but gives no detail.

205 MW in service

PhaseMWStatusDateSource
Vega single-building facility205operational2025-06-30The single-building facility, spanning 162,000 square feet, is powered by 205 MW of nameplate capacity behind-the-meter by a wind farm and front-of-the-meter by the ERCOT grid.
2026-02-24 View cached copy (2026-08-31)Live source ↗

Assessed October 9, 2026 from the newest filings, releases and reporting that name this project (newest relied on: August 14, 2026).

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today205 MW2025-08-06Vega initial energization
Contracted a customer is on the hook205 MW2025-08-06Vega colocation for BITMAIN and American Bitcoin
Under construction205 MW2025-05-07Vega site energization
Permitted--
Interconnect approved utility has agreed to deliver--
Interconnect requested in a queue, nothing approved--
Announced a press-release figure205 MW2025-05-07Vega site capacity

Who has claimed this site

Capacity commitments in the order they were announced. A commitment that ended shows why.

2025-08-06
Bitmain Technologies Limited - tenant · 205 MW source
2025-08-06
American Bitcoin - offtaker source

Claims about this project

2025-05-07 - stated
2025-05-07 - verified
Vega site energization 205.0 MW. Promised by 2025-06-30.
2025-08-06 - stated