205 MW Vega site energization in Q2 2025
Company: Hut 8
What the later record shows
Delivered; the record does not say when
The 2025 10-K describes Vega as a built site with a new data center form factor, which indicates it is operating. It gives no energization date or MW figure.
“At our Vega site, we pioneered a new data center form factor that challenges conventional assumptions about ASIC compute infrastructure”
2026-02-24 · Hut 8 10-K filed 2026-02-25 View cached copy (2026-08-31)Live source ↗
Checked October 25, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Hut 8 says its 205 MW Vega site is on track to energize in Q2 2025.
Source (primary)
hut-8 8-K exhibit (hut-20241113xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗
Quote: “The site is on track to energize in Q2 2025.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms hut-8 8-K exhibit (hut-20241113xex99d1.htm)
Quote: “The site is on track to energize in Q2 2025.”
confirms Hut 8 10-K filed 2026-02-25
Quote: “At our Vega site, we pioneered a new data center form factor that challenges conventional assumptions about ASIC compute infrastructure”