Vega colocation for BITMAIN and American Bitcoin
Company: Hut 8 - Project: Vega
The claim, verbatim
Upon full ramp, Hut 8 expects to provide up to 205 MW of ASIC Colocation capacity at Vega to BITMAIN and, via its purchase option, American Bitcoin.
Source (primary)
hut-8 8-K exhibit (hut-20250807xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-08)Live source ↗
Quote: “Commercialized Vega, where upon full ramp we expect to provide up to 205 megawatts of ASIC Colocation capacity to BITMAIN, and through the execution of our purchase option, American Bitcoin.”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The press release states Hut 8's expectation to provide up to 205 MW of ASIC Colocation capacity at Vega to BITMAIN and, via the purchase option, American Bitcoin.
Confirmed in the source:
- Hut 8 commercialized Vega
- Upon full ramp, Hut 8 expects to provide up to 205 MW of ASIC Colocation capacity at Vega
- The capacity is to go to BITMAIN and, through execution of Hut 8's purchase option, American Bitcoin
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1964789/000155837025010632/hut-20250807xex99d1.htm) in full (22,441 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms hut-8 8-K exhibit (hut-20250807xex99d1.htm)
Quote: “Commercialized Vega, where upon full ramp we expect to provide up to 205 megawatts of ASIC Colocation capacity to BITMAIN, and through the execution of our purchase option, American Bitcoin.”