NTL2

Project of WhiteFiber

Kind
datacenter
Location
Montreal area, Quebec
State/region
Quebec
Country
CA
Status
announced

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today--
Contracted a customer is on the hook--
Under construction5 MW2026-08-14NTL2 capacity development
Permitted--
Interconnect approved utility has agreed to deliver--
Interconnect requested in a queue, nothing approved--
Announced a press-release figure--

Claims about this project

2025-07-10 - stated
2025-07-10 - delayed
MTL-2 completion and revenue start. Promised by 2026-01-31.
2025-07-22 - stated
2025-07-28 - delayed
MTL-2 completion timeline. Promised by 2025-12-31.
2025-07-31 - delayed
MTL-2 operational completion. Promised by 2025-12-31.
2025-08-07 - delayed
MTL-2 completion timeline. Promised by 2025-12-31.
2026-03-25 - stated
2026-03-25 - stated
2026-03-25 - stated
2026-03-25 - stated
2026-03-25 - stated
2026-03-25 - stated
2026-08-14 - stated
NTL2 capacity development 5.0 MW. Promised by 2026-12-31.