MTL-2 operational completion
Company: WhiteFiber - Project: NTL2
What the later record shows
The date slipped · new target December 31, 2026
Development at NTL2 (about 5 MW, Canadian portfolio) was paused and only resumed in 2026. Completion is now targeted around year-end 2026 instead of Q4 2025.
“We had paused development while we evaluated the best use of that site. We've now decided to move forward.”
2026-08-14 · White Fiber (WYFI) Q2 2026 Earnings Call: NC1 Ramp and $540M+ Cloud Deals - TradingKey View cached copy (2026-08-31)Live source ↗
“NTL2’s approximately 5 megawatts of gross capacity targeted for completion around year-end 2026.”
2026-08-14 · White Fiber (WYFI) Q2 2026 Earnings Call: NC1 Ramp and $540M+ Cloud Deals - TradingKey View cached copy (2026-08-31)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
MTL-2 data center expected to be completed and operational in fourth quarter of 2025 with one-month delay before revenue generation
Source (primary)
WhiteFiber S-1/A filed 2025-08-01 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “The MTL-2 data center is expected to be completed and operational in the fourth quarter of 2025 with a one-month delay before it begins to generate revenue.”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The prospectus summary says MTL-2 is expected to be completed and operational in Q4 2025, with a one-month delay before revenue begins.
Confirmed in the source:
- MTL-2 is expected to be completed and operational in the fourth quarter of 2025
- MTL-2 is expected to have a one-month delay after becoming operational before it begins generating revenue
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025070709/ea0249945-04.htm) in full (845,158 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WhiteFiber S-1/A filed 2025-08-01
Quote: “The MTL-2 data center is expected to be completed and operational in the fourth quarter of 2025 with a one-month delay before it begins to generate revenue.”
delays White Fiber (WYFI) Q2 2026 Earnings Call: NC1 Ramp and $540M+ Cloud Deals - TradingKey
Quote: “We had paused development while we evaluated the best use of that site. We've now decided to move forward.”