MTL-2 completion timeline
Company: WhiteFiber - Project: NTL2
What the later record shows
The date slipped · new target December 31, 2026
In August 2026 the company said it had paused development at NTL2, the roughly 5 MW Canadian site listed alongside MTL1 and MTL3, and now targets completion around year-end 2026. So it was not operational in Q4 2025.
“We had paused development while we evaluated the best use of that site. We've now decided to move forward.”
2026-08-14 · White Fiber (WYFI) Q2 2026 Earnings Call: NC1 Ramp and $540M+ Cloud Deals - TradingKey View cached copy (2026-08-31)Live source ↗
“NTL2’s approximately 5 megawatts of gross capacity targeted for completion around year-end 2026.”
2026-08-14 · White Fiber (WYFI) Q2 2026 Earnings Call: NC1 Ramp and $540M+ Cloud Deals - TradingKey View cached copy (2026-08-31)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
MTL-2 expected to be completed and operational in Q4 2025 with one-month delay before revenue generation
Source (primary)
WhiteFiber 424B4 filed 2025-08-08 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “The MTL -2 data center is expected to be completed and operational in the fourth quarter of 2025 with a one -month delay before it begins to generate revenue.”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The prospectus states both the Q4 2025 completion expectation and the one-month revenue delay.
Confirmed in the source:
- MTL-2 is expected to be completed and operational in Q4 2025
- There is expected to be a one-month delay before MTL-2 begins generating revenue
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025073279/ea0249945-07.htm) in full (825,843 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WhiteFiber 424B4 filed 2025-08-08
Quote: “The MTL -2 data center is expected to be completed and operational in the fourth quarter of 2025 with a one -month delay before it begins to generate revenue.”
delays White Fiber (WYFI) Q2 2026 Earnings Call: NC1 Ramp and $540M+ Cloud Deals - TradingKey
Quote: “We had paused development while we evaluated the best use of that site. We've now decided to move forward.”