Wyoming Property
Project of CleanSpark
Where it stands
CleanSpark bought the Cheyenne, Wyoming land from MineOne in 2024. By March 31, 2025, one Wyoming data center was active and a second was under development. By June 30, 2025, both were operating, and the FY2025 10-K reports two fully constructed immersion mining facilities in Cheyenne backed by about 110 MW combined (3.52 EH/s). The 110 MW figure covers both Wyoming sites together, with no per-site split. Later filings through June 2026 still list Wyoming in the portfolio, but none gives an updated Wyoming MW figure.
110 MW in service
| Phase | MW | Status | Date | Source |
|---|---|---|---|---|
| Cheyenne facility 1 | operational | 2025-03-31 | one active data center, with another under development, in Wyoming as of March 31, 2025 2025-05-07 View cached copy (2026-08-31)Live source ↗ | |
| Cheyenne facility 2 | operational | 2025-06-30 | twelve data centers in Tennessee, and two data centers in Wyoming as of June 30, 2025 2025-08-06 View cached copy (2026-08-31)Live source ↗ |
Assessed October 18, 2026 from the newest filings, releases and reporting that name this project (newest relied on: August 5, 2026).
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | -- | ||
| Contracted a customer is on the hook | 75 MW | 2024-12-02 | Wyoming mining locations operational timeline |
| Under construction | 75 MW | 2024-12-02 | Wyoming mining facility expansion |
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 75 MW | 2024-05-08 | Wyoming property power capacity |