Wyoming Property

Project of CleanSpark

Kind
mining
Location
Wyoming
State/region
WY
Country
US
Status
announced

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today--
Contracted a customer is on the hook75 MW2024-12-02Wyoming mining locations operational timeline
Under construction75 MW2024-12-02Wyoming mining facility expansion
Permitted--
Interconnect approved utility has agreed to deliver--
Interconnect requested in a queue, nothing approved--
Announced a press-release figure75 MW2024-05-08Wyoming property power capacity

Claims about this project

2024-05-08 - stated
2024-05-08 - stated
2024-05-08 - stated
2024-12-02 - delayed
Wyoming mining facility expansion 75.0 MW. Promised by 2025-03-31.
2024-12-02 - stated