jain.com

Wyoming mining facility capacity

Company: CleanSpark - Project: Wyoming Property

Subject kind
facility capacity
Statement date
2024-12-02
Promised amount
75.0 MW
Current status
stated

The claim, verbatim

Two Wyoming mining locations expected to have approximately 75 MW of data center infrastructure power under contract

Source (primary)

CleanSpark 10-K filed 2024-12-03 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “are expected to have approximately 75 MW of data center infrastructure power under contract.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms CleanSpark 10-K filed 2024-12-03

Quote: “are expected to have approximately 75 MW of data center infrastructure power under contract.”

View cached copy (2026-08-31)Live source ↗