Wyoming mining facility expansion

Company: CleanSpark - Project: Wyoming Property

Subject kind
facility timeline
Statement date
2024-12-02
Promised by
2025-03-31
Promised amount
75.0 MW
Current status
verified

What the later record shows

Delivered late · happened June 30, 2025

As of March 31, 2025, the promised date, the 10-Q still listed one active Wyoming data center with another under development. By June 30, 2025, CleanSpark reported operating two Wyoming data centers, and by September 30, 2025 both immersion-cooled sites were backed by about 110 MW, so the second site came online late, sometime in the April–June 2025 quarter.

“one active data center, with another under development, in Wyoming as of March 31, 2025”
2025-05-07 · CleanSpark 10-Q filed 2025-05-08 View cached copy (2026-08-31)Live source ↗
“fourteen data centers in Georgia, five data centers in Mississippi, twelve data centers in Tennessee, and two data centers in Wyoming as of June 30, 2025”
2025-08-06 · CleanSpark 10-Q filed 2025-08-07 View cached copy (2026-08-31)Live source ↗
“we operate two wholly owned mining facilities in Wyoming, both of which utilize immersion cooling technology to enhance efficiency and performance”
2025-11-24 · CleanSpark 10-K filed 2025-11-25 View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Two Wyoming mining locations under construction expected to become operational between first and second quarter of fiscal year 2025 with approximately 75 MW of data center capacity

Source (primary)

CleanSpark 10-K filed 2024-12-03 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “We have two separate mining locations in Wyoming that are under construction and are expected to be operational between the first and second quarter of fiscal year 2025. These locations will include miners that are cooled through immersion technology, a method of submerging mining hardware in a non-conductive fluid to cool the equipment and improve its efficiency, and are expected to have approximately 75 MW of data center infrastructure power under contract.”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The 10-K states that two Wyoming locations are under construction and expected to be operational between Q1 and Q2 of fiscal 2025. It describes them as having approximately 75 MW of data center infrastructure power under contract, and the MD&A separately refers to finalizing 75 MW of development in Wyoming.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/827876/000095017024132565/clsk-20240930.htm) in full (484,491 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark 10-K filed 2024-12-03

Quote: “We have two separate mining locations in Wyoming that are under construction and are expected to be operational between the first and second quarter of fiscal year 2025. These locations will include miners that are cooled through immersion technology, a method of submerging mining hardware in a non-conductive fluid to cool the equipment and improve its efficiency, and are expected to have approximately 75 MW of data center infrastructure power under contract.”

View cached copy (2026-08-31)Live source ↗

confirms CleanSpark 10-Q filed 2025-05-08

Quote: “one active data center, with another under development, in Wyoming as of March 31, 2025”

View cached copy (2026-08-31)Live source ↗

confirms CleanSpark 10-Q filed 2025-08-07

Quote: “fourteen data centers in Georgia, five data centers in Mississippi, twelve data centers in Tennessee, and two data centers in Wyoming as of June 30, 2025”

View cached copy (2026-08-31)Live source ↗

confirms CleanSpark 10-K filed 2025-11-25

Quote: “we operate two wholly owned mining facilities in Wyoming, both of which utilize immersion cooling technology to enhance efficiency and performance”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 3, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 4, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.