Auburn
Project of Core Scientific
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | 50 MW | 2026-03-01 | Auburn, Alabama facility |
| Contracted a customer is on the hook | 11 MW | 2026-09-01 | Auburn, Alabama HPC data center lease |
| Under construction | -- | ||
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 30 MW | 2026-09-01 | Auburn billable power capacity available for colocation |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
2026-07-27
Undisclosed counterparty (one or more) - tenant ยท 15-year term source
2026-07-27
Advanced Micro Devices - guarantor source
Claims about this project
2026-03-01 - stated
Auburn, Alabama facility 50.0 MW.
2026-09-01 - stated
Auburn AL site delivery. Promised by 2027-06-30.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated